Medical Device Storage
Tennessee
Scope
Pallet rack supply and installation
Custom In-House Fabricated Reel Rack
Oklahoma · 10 days to install · 7 installers
800 x 600
Custom in-house fabricated reel rack, close-up of bay construction: Oklahoma
Medical Manufacturing: New Rack Install
Memphis · 3 days to install
800 x 600
New pallet rack installed at a medical manufacturing facility: Memphis
Multi-Phase Double Deep Rack System
Memphis · 8 weeks faster than new rack
Tear Down & Reconfiguration
Memphis · 7 days to install
800 x 600
Crew mid-teardown/reconfiguration of an existing pallet rack system: Memphis
System
Drive-in pallet rack
Scope
Full teardown and reconfiguration of the existing system
21,500 Sq Ft Warehouse
Memphis · 4 days to install
1,000 Sections of Teardrop Speedrack Teardown
Chicago
800 x 600
Large-scale teardrop speedrack teardown in progress: Chicago
458,000 Sq Ft Warehouse
Tennessee · 9 days to install
300,000 Sq Ft Warehouse
Wisconsin · 24 days to install · combination of used and new material
800 x 600
Mixed new/used rack installation, 300,000 sq ft facility
“American Material Handling was quick, resourceful and flexible to convert their project ideas to reality. The material delivered was as agreed and the installation was professionally done according to schedule. We are happy with the outcome.”
500,000 Sq Ft Warehouse
Memphis
100,000 Sq Ft Warehouse
Hastings, NE · 7 days to install
800 x 600
Completed pallet position rack rows: Hastings, NE
350,000 Sq Ft Teardown
Memphis · 3 weeks
800 x 600
Large-scale rack teardown crew and equipment on-site: Memphis